G3 building
grain export terminal
at Port of Vancouver

2016-12-28

McKeil Marine's Evans Spirit  won the International Bulk Journal's 2016 Ship of the Year Award during the IBJ's Salute to Excellence in the Maritime Bulk Industry gala awards ceremony in London, UK on November 21.
"It's a fantastic way to closeout our 60th anniversary year: having a vessel named after our founder, Evans McKeil, win this prestigious international award," said Steve Fletcher, President and CEO of McKeil Marine.
Acquired by McKeil in 2015, the Evans Spirit is a cargo ship with the shallow draught characters of a tug and barge; however, compared to a tug-and-barge unit, she can transport approximately 40 per cent more cargo about 50 per cent faster on a very similar amount of fuel.  She is in service throughout the Great Lakes and St. Lawrence River.
Evans Spirit was shortlisted for 2016 Ship of the Year competing with three other vessels: CS Bright, Mitsui OSK Lines, Japan;  Damen Shipyards, Netherlands; and MN Baroque, Swiss Marine, Switzerland. The award is presented to the owner, operator or builder of an outstanding individual bulk ship. Judged on operational efficiency, design innovation, safety and environmental protection, the Evans Spirit was selected as winner. (Photo Paul Beesley).

G3 Terminal Vancouver, an affiliate of G3 Global Holdings (G3), will build a state-of-the-art grain export terminal in North Vancouver, British Columbia, the first new grain terminal constructed at the Port of Vancouver since the 1960s.

"Our Vancouver terminal is central to G3's vision of a coast-to-coast grain handling network that sets a new standard in efficiency," said Karl Gerrand, CEO G3. "We plan to transform the movement of grain through the west coast, providing Canadian farmers with competitive pricing and reliable delivery opportunities."

G3's Vancouver terminal will feature a rail loop track that will be capable of holding three 134-car trains, unique to grain exporting terminals in Canada. The terminal includes over 180,000 metric tonnes of storage and will be able to handle cereal grains, oilseeds, pulses and special crops, much of which will be supplied via a throughput agreement with G3 Canada Limited, the companies said.

This will allow trains to travel to Vancouver, unload while in continuous motion, and travel back to G3 Canada's primary elevators, including four recently constructed primary elevators, without detaching from their locomotives, critical to increasing supply chain efficiency.?In addition to improved rail efficiency, G3's Vancouver facility was designed with a focus on high velocity receiving, shipping, and best-in-class environmental and safety standards.?

The development of G3's Vancouver terminal will be led by Bill Mooney, who has extensive Vancouver grain terminal management experience, together with G3's team of experienced project engineers. Peter Kiewit Infrastructure Co. has been selected as the design-build contractor for the project. Construction will commence in March 2017, subject to final notifications, with the terminal slated for completion in 2020.

 